E2-2 – Actions and resources related to pollution
🗂️ ESRS E2 Pollution, page 4
-
The undertaking shall disclose its pollution-related actions and the resources allocated to their implementation.
-
The objective of this Disclosure Requirement is to enable an understanding of the key actions taken and planned to achieve the pollution-related policy objectives and targets.
-
The description of the pollution-related action plans and resources shall contain the information prescribed in ESRS 2 MDR-A Actions and resources in relation to material sustainability matters.
-
In addition to ESRS 2 MDR-A, the undertaking may specify to which layer in the following mitigation hierarchy an action and resources can be allocated:
(a) avoid pollution including any phase out of materials or compounds that have a negative impact (prevention of pollution at source);
(b) reduce pollution, including: any phase-out of materials or compounds; meeting enforcement requirements such as Best Available Techniques (BAT) requirements; or meeting the Do No Significant Harm criteria for pollution prevention and control according to the EU Taxonomy Regulation and its Delegated Acts (minimisation of pollution); and
(c) restore, regenerate and transform ecosystems where pollution has occurred (control of the impacts both from regular activities and incidents).
Application Requirements
Section titled “Application Requirements”AR 13. Where actions extend to upstream or downstream value chain engagements, the undertaking shall provide information on the types of actions reflecting these engagements.
AR 14. When considering resources, examples of operational expenditures could be investments in research and development to innovate and develop safe and sustainable alternatives to the use of substances of concern or to decrease emissions in a production process.
AR 15. Where relevant to achieve its pollution-related policy objectives and targets, the undertaking may provide information on site-level action plans.